Right Panel Commands on the S3 // Risk Tab
Use these commands to select the right panel view.
Field | Description |
---|---|
None | When you select this option, then the view you selected in the Left Panel menu displays in the entire Acumen window. |
Gantt Chart | Click this command to view the project schedule in Gantt chart format.
This command does not display when you select Risk Register from the menu. |
Uncertainty Inputs | Click this command to view the breakdown of uncertainty inputs.
This command does not display when you select Risk Register from the menu. |
Risk Exposure | Click this command to view and evaluate risk exposure in a histogram.
This command does not display when you select Risk Register from the menu. |
Risk Exposure Comparison | Use the Risk Exposure view to add multiple risk exposure scenarios to the risk comparison then click this command to compare those results using a tornado chart. |
Risk Drivers | Click this command to view cost and schedule risk drivers in a tornado chart. Use the
This command does not display when you select Risk Register from the menu. |
menu to customize the chart, including setting bar mode and detail levels and adding vertical scrolling.
Risk Driver Comparison | Use the Risk Drivers view to add the current result set to the risk driver comparison, then click this command to compare those result sets in a single chart. |
Risk Sensitivity | Click this command to view relationship and joint confidence level (JCL) between activities and/or costs in a scatter chart.
This command does not display when you select Risk Register from the menu. |
Critical Schedule Drivers | Click this command to view critical paths and near-critical paths that become critical due to risk.
This command does not display when you select Risk Register from the menu. |
Risk Register | Click this command to create and maintain project risks and integrate them into cost/schedule model.
The Details form for the Risk Register are found here. |
Activities | Click this command to view the project schedule and set duration uncertainties.
This command only displays when you select Risk Register from the menu. |
Mitigation Analysis | After you have created risk mitigation steps and assigned risks to activities, select this option to run risk analysis with mitigation for the selected risk event to compare mitigation steps. Acumen runs the analysis using each mitigation step then displays a Mitigation Steps chart that shows you how the mitigation affects the schedule. |
For example, if the selected risk has four mitigation steps, Acumen runs the analysis with no mitigation, then runs the analysis using mitigation step 1, then steps 1 and 2, then steps 1 through 3, then steps 1 through 4.
This command only displays when you select Risk Register from the menu. |